Project Profiles M.O.D.

Whittington Barracks

Analysis

  • Contract Value£775k
  • Principal ContractorSkerritt Ltd
  • ClientMinistry of Defence
  • Contract Duration24 weeks
  • Supervising OfficerWhite Young Partners

Summary

The works consisted of the disconnection and removal of all existing redundant HTHW and LTHW heating calorifiers, pumps, controls, pipework , fittings and associated components. Also the removal of DHWS within 14 plant rooms.

  • Supply Install Test and Commission
  • New Boiler Plant
  • DHWS Calorifiers
  • Pressurisation Units
  • Flues
  • BMS Control System
  • 5 New Boiler Rooms
  • New MDPE Underground gas mains to new boiler rooms
  • BMS loop around the site
  • New Alarm System
  • Lighting
  • Small Power
  • Mechanical Controls
  • Temporary Plant through transition stage



Whittington Barracks Whittington Barracks