Gibraltar Barracks, Minley.

Analysis

  • Contract Value£1.8M
  • Principal ContractorSkerritt Ltd
  • ClientMinistry of Defence
  • Contract Duration43 Weeks
  • Supervising OfficerSymonds Group

Summary

The decentralisation of the existing MTHW systems and the construction and installation of 13 new plant rooms.

Supply and installation of the new plant and equipment, to provide the LTHW services and hot and cold water services to the existing buildings. Each plant room also included the builder\'s works, electrical lighting and power and BMS control systems linked to the site-wide LAN and control PC / server.

Supply and installation of the heating to the Sports Hall, and ventilation\'s (AHU\'s) to the Sports Hall, Swimming Pool, Cinema and Sergeants Mess buildings

The supply and installation of the site-wide gas supply to the 13 new plant rooms, complete with all gas meters, solenoid valves and governors

Gibraltar Barracks Gibraltar Barracks